PRIVASIA kicks off RM569mil data centre construction in Perak (The Star : 2 Dec 2025)

Dec 02, 2025
PRIVASIA kicks off RM569mil data centre construction in Perak (The Star : 2 Dec 2025)

PETALING JAYA: PRIVASIA Technology Bhd has moved into the execution phase of its flagship data centre project in Perak after awarding a RM569mil engineering, procurement, construction and commissioning (EPCC) contract to Inspur Communication Malaysia Sdn Bhd.

In a filing to Bursa Malaysia, the company said its indirect wholly owned subsidiary, SILVERSTREAMS Technofarm Sdn Bhd, had issued a letter of award to Inspur to build a 10.06MW information technology load data centre in Bagan Datuk.

The RM569mil contract was accepted on Dec 2, with works slated to begin within 15 days of acceptance and an 18-month completion timeline. The scope covers the full stack from design and procurement through construction and commissioning.

While the contract is not expected to have an immediate impact on earnings for the financial year ending December 2025, the group said the development is expected to “contribute positively to future earnings” once operational.

The board added that no exceptional risks are foreseen beyond typical construction, regulatory and execution risks, and confirmed that no shareholder or regulatory approvals are required.

___________________

Corporate News | TheStar.com.my 
2 Dec 2025

BUSINESS HIGHLIGHTS

Previous
Next
Dec 27, 2025
Ahmad Zahid, yang juga Menteri Kemajuan Desa dan Wilayah, berkata beliau berada di Bagan Datuk bagi meninjau perkembangan beberapa projek pembangunan strategik yang dirancang demi menjamin kemakmuran serta kesejahteraan rakyat...
Dec 02, 2025
PRIVASIA Technology Bhd has moved into the execution phase of its flagship data centre project in Perak after awarding a RM569mil engineering, procurement, construction and commissioning (EPCC) contract to Inspur...
Nov 12, 2025
PRIVASIA said the project will now be spearheaded by its subsidiary, SILVERSTREAMS Technofarm Sdn Bhd. The subsidiary will be responsible for all aspects of the project, including funding, feasibility studies,...
Dec 11, 2024
Timbalan Perdana Menteri, Datuk Seri Dr Ahmad Zahid Hamidi, berkata pembangunan itu turut membuktikan sinergi dan usaha sama strategik antara kerajaan serta swasta yang memberi manfaat kepada Perak dan keseluruhan...
Dec 11, 2024
Mara Inc and ACE Market-listed PRIVASIA Technology Bhd, a business process outsourcing company, are teaming up to develop and operate a data centre in Bagan Datuk, Perak.